The works will commence after the holiday period from Monday 6 January and traffic management will be installed from 08:00hrs and remain in place for approx. 7 weeks.
Unfortunately, it is not an option to put the traffic management in and out on a daily basis and this will have an impact on traffic movement around the works for the duration.
The works will require a lane closure over the full duration as we carry out the following:
- Reconfiguration of 2 traffic islands
- Adjustment of kerb lines
- Resurfacing
- Improved signage and road markings
I appreciate your continued understanding and patience as we complete these works on behalf of Tilbury2.